Fermi Inc reports receipt of US$200M hyperscaler prepayment
The Nov. 23 filing does not say whether the money is restricted or update the status of a long-term lease at Project Matador.

A US$200 million customer advance is in hand for a proposed power development in the Texas Panhandle. Fermi Inc. NASDAQFRMI LONFRMI, the Dallas private-grid developer behind the 600-megawatt plan, said in a Nov. 23 filing that it had received the amounts due under the hyperscaler prepayment agreement.
Fermi shares NASDAQFRMI were up at US$2.26 as of 11:33 a.m. EST on Nov. 23. The London listing LONFRMI was also quoted higher, at US$2.26 as of 4:38 p.m. GMT on Nov. 23.
The Nov. 23 filing refers to the prepayment agreement from the Nov. 12 earnings call, where management gave the amount and said it would help develop power for an unnamed investment-grade customer at Project Matador. The filing does not attach the agreement or say whether the money is restricted or refundable under any circumstances.
The advance puts customer cash behind the power development, alongside a separate early construction and site development agreement that sets out how site preparation can begin. The Nov. 23 report gives no spending schedule or budget for delivering the 600 megawatts, leaving the share of development costs covered by the advance undisclosed.
The Hyperscaler Would Build Its Own Data Centres
Fermi would supply the power, land and supporting infrastructure, while the hyperscaler would design and build its own data centres. Fermi said that structure leaves it without the cost of building those facilities, though it would still be developing the capacity to power them. The Nov. 23 filing confirms the funding but gives no update on the long-term lease management was pursuing on Nov. 12.
“We continue to work toward a definitive long-term lease, and the customer’s identity remains confidential,” Fermi chief executive Lee McIntire said on the Nov. 12 call.
McIntire contrasted the deal with a turnkey lease that Fermi said on Nov. 12 would not proceed. He said the earlier transaction had depended on third-party credit, while the proposed 600-megawatt development was arranged directly with the investment-grade hyperscaler.
The more than two gigawatts McIntire cited on Nov. 12 described the generation equipment Fermi had secured for the campus rather than power delivered to the customer. Fermi had already brought equipment onto the site and carried out engineering and site preparation work, he said. He put Fermi's investment in the site at more than US$1.6 billion.
The Nov. 12 investor presentation put the campus at about 8,400 acres acquired, under contract or under option. Its model for this deal leaves Fermi responsible for campus infrastructure such as water and fibre. The presentation also showed a powered shell offering, under which Fermi would provide the building as well. The tenant would be responsible for cooling and the data halls under either option.
An Odessa Compute Project Has a First-Phase Order
The AI compute deployment in Odessa offers a comparison for how developers fund their first phase. ChronoScale Holdings Corporation NASDAQCHRN, a provider of dedicated computing infrastructure for AI workloads, said in its Nov. 18 release that the first 65 megawatts of that deployment had been ordered. It scheduled the phase for the first half of 2027.
ChronoScale also outlined US$250 million in equity financing and a convertible preferred facility of up to US$500 million on Nov. 18. The company would still have part of its development partnership contribution to fund after using the common equity proceeds. It named future project financing as a possible source for the balance, along with existing cash and other capital.
ChronoScale said its right of first offer covers the remaining 285 megawatts of planned campus capacity. Orders are still needed for the second and third phases to go ahead, and the Nov. 18 announcement said the customer had not committed to them. ChronoScale shares NASDAQCHRN were quoted at US$9.33 as of 10:34 a.m. EST on Nov. 23.
Read more: ChronoScale signs Odessa AI partnership with up to US$7.5B in initial contract value
Fermi Targets First Power in 2027
Some of the preparations predate the funding confirmation. On the Nov. 12 call, Fermi said it had secured structural steel that the customer could use to speed up construction. McIntire said Fermi had already installed 4.6 miles of gas pipeline on the site.
The hyperscaler is planning its build around the point when power first becomes available, Fermi chief commercial officer Anna Bofa said on Nov. 12. The target sets no date for delivery of all 600 megawatts. Fermi is aiming to reach that first milestone late in the second quarter or early in the third quarter of 2027.
Julian Okafor