Applied Digital Corporation signs US$5.4B AI data centre lease

Deliveries under the 18-year, 150-megawatt lease could start in the first half of 2028 pending development milestones, utility arrangements and regulatory approvals.

Julian Okafor·
A steel object and a railing are visible in an unfinished structure.
A construction scene with steel and a railing. Illustration: Mugglehead, generated with AI.

A new AI data centre lease carries about US$5.4 billion in contracted revenue over its initial term, with the first capacity deliveries expected in 2028. Applied Digital Corporation NASDAQAPLD, the Dallas-based builder and operator of AI data centre campuses, said Monday it entered into an 18-year lease for 150 megawatts of critical IT capacity with a hyperscaler it described as investment grade.

Applied Digital shares rose about 27 per cent to US$14.59 on Nasdaq at 10:37 a.m. EST Monday, according to NASDAQAPLD. The developer also announced a US$300 million senior secured bridge facility in a separate Nov. 23 announcement.

The Nov. 23 lease release did not name the tenant, identify the campus or include the lease text. It also did not say whether the customer must pay for all 150 megawatts regardless of use. Applied Digital listed the signing and regulatory approval of power supply agreements among general risks to lease effectiveness. The release did not say whether either step was required for this agreement to take effect.

Applied Digital says deliveries depend on reaching development milestones, having utility arrangements in place and obtaining regulatory approvals. The company is targeting the first half of 2028 for those initial deliveries. The Nov. 23 announcement did not specify when the lease commences or when the first payment is due.

Renewals Could Take the Lease to 33 Years

The new lease could generate about US$12.7 billion if the tenant exercises all its renewal options. The Nov. 23 base-term estimate works out to an average of about US$300 million a year over 18 years. Applied Digital says pricing is higher than under earlier agreements, but the release gives no schedule showing how payments are spread across the term.

The agreement puts Applied Digital's total contracted base-term lease revenue above US$41 billion as of Nov. 23. The company estimates that figure could reach about US$100 billion across the portfolio if customers exercise all renewal options. It says investment-grade customers account for about 75 per cent of base-term contracted lease revenue.

Applied Digital reported more than 1.6 gigawatts of contracted critical IT load across its portfolio after adding the lease. That is the power committed for customers' computing equipment, separate from the 2.2 gigawatts the company reports for peak grid-connected load. Neither figure measures how much capacity has begun earning rent.

The Build Still Needs Project Financing

Applied Digital says it has funded the initial equity for the build from its balance sheet and its preferred equity program, with project financing to follow. Its Nov. 23 lease release did not give a dollar figure for the initial equity or the project financing it expects to raise.

The broader preferred equity facility has a US$5 billion ceiling, according to an Oct. 7, 2025 funding announcement. Funds managed by Macquarie Asset Management provided the first US$112.5 million draw on that date to support the build at the 400-megawatt Polaris Forge 1 project in North Dakota. The Nov. 23 lease release did not give a draw amount for the new build.

ChronoScale Holdings Corporation NASDAQCHRN, a provider of graphics-processor capacity, said in its Nov. 18 release that the initial order at an Odessa, Texas, campus covers 65 megawatts. Applied Digital contributed its cloud business to Ekso in May, and the combined company took the ChronoScale name. The Odessa deal covers compute capacity, a different revenue stream from leasing data centre space and power.

ChronoScale shares rose about 17 per cent to US$9.33 on Nasdaq at 10:34 a.m. EST Monday, according to NASDAQCHRN. ChronoScale's Nov. 18 announcement puts deployment of the ordered capacity in the first half of 2027, a year ahead of the first deliveries Applied Digital expects under the new lease.

Read more: ChronoScale signs Odessa AI partnership with up to US$7.5B in initial contract value

“We expect to complete the remaining project finance for Delta Forge 1 and Polaris Forge 3 in the first calendar quarter of 2027,” Applied Digital chief financial officer Saidal Mohmand said in the Nov. 23 lease release.

Mohmand put Delta Forge 2 financing in the second quarter of 2027. Those financing targets cover named projects, while the first deliveries under the new lease are expected in the first half of 2028 if the project's development, utility and regulatory conditions are met.