ChronoScale signs Odessa AI partnership with up to US$7.5B in initial contract value
Financing of up to US$750 million includes a conditional preferred facility of up to US$500 million, and the first common sale is expected to gross US$153 million.

The first 65 megawatts ordered at a data centre campus in Odessa, Texas, carry a projected contract value of up to US$7.5 billion over six years. ChronoScale Holdings Corporation NASDAQCHRN, a provider of graphics processor capacity for AI workloads, said Wednesday it signed definitive agreements for an equal development partnership with campus developer STN, Inc. and up to US$750 million in financing.
ChronoScale's Nov. 18 release puts the value of each partner's contribution at US$390 million. Their contributions for equal stakes are subject to antitrust clearance under the Hart-Scott-Rodino Act. The contract-value projection is for the venture, in which ChronoScale would initially receive half the profits and bear half the losses.
ChronoScale shares fell 4.31 per cent to US$9.32 on Nasdaq at 12:57 p.m. EST Wednesday, according to NASDAQCHRN. The company expects its initial common-stock sale to bring in US$153 million in gross proceeds, according to its Nov. 18 filing.
ChronoScale expects to send its preferred investor a notice for an initial US$10 million purchase on Nov. 18. The first phase of the campus is scheduled for deployment in the first half of 2027, with further capacity contingent on new orders.
The Initial Placement Would Add About 19 Million Shares
At 12:57 p.m. EST Wednesday, NASDAQCHRN displayed a previous close of US$9.74 and 145.64 million shares outstanding. The Nov. 18 placement price of US$8 was about 17.9 per cent below that previous close.
Using the displayed share count as a pre-placement estimate, issuing the approximately 19.1 million shares expected at the initial closing would increase the count by about 13.1 per cent. The shares sold at that closing would account for about 11.6 per cent of the enlarged common equity.
The Nov. 18 filing puts the issuance cap at 19.99 per cent of common shares issued and outstanding immediately before the common stock purchase agreement was signed. Shares issued or issuable in any transaction that may be aggregated with the placement under applicable Nasdaq rules reduce that cap.
Holders of a majority of ChronoScale's outstanding voting power gave written consent. The cap applies until the approval takes effect, which can happen no sooner than 20 calendar days after ChronoScale first sends or gives shareholders its definitive information statement.
Data centre operator Applied Digital Corporation NASDAQAPLD combined its cloud business with Ekso to form ChronoScale in May. Conversion of a note could give Applied Digital ChronoScale common shares in the fourth quarter of 2026. ChronoScale says Applied Digital will hold the note, which forms part of the US$250 million equity component announced Nov. 18. Applied Digital shares rose 2.32 per cent to US$14.55 on Nasdaq at 1:04 p.m. EST Wednesday, according to NASDAQAPLD.
Under the four-year preferred facility, ChronoScale can require the investor to buy up to US$500 million of Series C convertible preferred stock, subject to draw conditions. The Nov. 18 release puts the initial minimum conversion price at US$12 per share. The preferred purchase agreement sets the price at each share's stated value divided by 103 per cent, the Nov. 18 filing says. ChronoScale intends to use net proceeds from the preferred placement for working capital and general corporate purposes.
ChronoScale named hybrid-cloud software supplier Nutanix, Inc. NASDAQNTNX among the financing's four strategic participants. An Aug. 18 announcement from Nutanix said ChronoScale plans to use Nutanix software for functions including customer onboarding and service automation.
The First Order Covers 65 Megawatts
ChronoScale said an investment-grade technology company is providing credit support for a substantial portion of the first phase. The campus plan calls for 350 megawatts, with GPU configurations varying by phase. ChronoScale has a right of first offer on the remaining 285 megawatts, where expansion depends on new orders, agreed terms, permits, power and financing.
“We continue to see frontier AI moving beyond incremental compute expansion toward infrastructure commitments measured in hundreds of megawatts,” ChronoScale chief executive Cenly Chen said in the release.
ChronoScale used all three phases of its campus plan in the Nov. 18 revenue estimate. The blended projection comes to about US$20.8 million per megawatt a year. The company identified cash on hand, other existing capital and possible project financing as sources for the remainder of its contribution. ChronoScale intends to use net common-placement proceeds for part of that commitment, including campus construction and graphics processor purchases, and for general corporate purposes.
The six-year Odessa estimate comes from a customer contract. Mugglehead's Nov. 16 coverage of a proposed data centre acquisition tracked capital going into a portfolio of hyperscale facilities.
Read more: Blackstone Digital Infrastructure Trust agrees to US$5B data-centre deal
ChronoScale gave Nov. 18 as the target closing date for the partnership and the common placement, subject to their respective conditions. It scheduled deployment of the ordered 65 megawatts for the first half of 2027.