Namib Minerals pours first gold at Redwing mine in Zimbabwe

The company expects its higher-capacity winder to arrive by the end of the first quarter of 2027 as it works to raise ore throughput.

Mara Quinlan·
A cable wound around a hoist drum fills the right side of a generic mine winding house.
A shaft hoist drum illustrates the equipment needed to lift more ore at Redwing. Illustration: Mugglehead, generated with AI.

Namib Minerals NASDAQNAMM said on Monday it had poured first gold at Redwing in Zimbabwe, meeting its November target. The pour gives Namib a second producing mine alongside How Mine, with an initial target set Nov. 3 of about 338 ounces a month at Redwing.

Shares rose nearly four U.S. cents to US$0.6566 at 9:16 a.m. EST on Nov. 23 in Nasdaq premarket trading.

Namib described the pour as a return to commercial production but did not disclose the size of the pour or report a sustained production rate. The company said the initial phase would test whether the underground mine can supply the plant consistently.

Namib expects the higher-capacity winder to arrive by the end of the first quarter of 2027 and plans to install and commission it to lift more ore to the surface. The company says it intends to update the market on delivery, installation, commissioning and the demonstrated impact on hoisting capacity.

The Nov. 3 plan put initial throughput at about 3,600 tonnes of ore a month. Namib aimed to lift that to about 10,000 tonnes a month by the second quarter of 2027 and raise production to about 835 ounces of gold a month.

Monday's release did not restate the monthly targets and said higher output would depend on commissioning and performance at the mine and mill. Namib expects to issue 2027 production and cost guidance in the first quarter once it has enough operating data.

"Our focus now is to establish consistent, reliable production, demonstrate the operating performance of the mine and execute the planned ramp-up," Namib chief executive Tulani Sikwila said in the release.

Namib said on Nov. 3 that it brought the restart forward after Zimbabwe introduced production requirements for foreign-owned operators in the small and medium gold mining sector. The company finished dewatering in September and recommissioned the crushing plant in October as it prepared to restart using the existing workings and plant.

Namib puts Redwing's historical output at about 650,000 ounces from 1981 through 2023. The feasibility study will assess whether the mine can be redesigned to produce more gold.

Namib's July 20 development schedule calls for 8,750 metres of drilling after the funded technical phase, but the drilling depends on the company securing the next stage of financing.

In Ethiopia, Allied Gold Corporation TSEAAUC NYSEAAUC announced first gold at Kurmuk on Nov. 9. In a Nov. 18 update, it still expected to start selling gold in December and reach commercial production by the end of 2026.

Read more: Allied Gold targets year-end Kurmuk commercial production as grid work advances

Namib expects to finish the technical phase of the Redwing feasibility study early in the first quarter of 2027.