Entrée Resources agrees framework with Mongolian government for licence talks
Entrée also reported 125.31 metres grading 1.45 per cent copper equivalent from infill hole UGD1025A at Hugo North Extension.

Entrée Resources Ltd. TSEETG OTCMKTSERLFF said on Friday it had agreed a framework for talks with a Mongolian government working group that aims to resolve outstanding issues on its Shivee Tolgoi and Javkhlant licences within the first quarter of 2027. Entrée holds a 20 or 30 per cent carried interest in the licence area, depending on depth, through its joint venture with Oyu Tolgoi LLC.
Entrée shares closed unchanged at C$2.12 in Toronto before the release, according to the Google Finance quote page for TSEETG at 4:00 p.m. EST on Nov. 26.
The company said in its Nov. 5 third-quarter release that the licences must pass to Oyu Tolgoi LLC before Lift 1 Panel 1 lateral development on the Shivee Tolgoi licence can proceed.
The same release said the licences lie within the Oyu Tolgoi strategic deposit. Mongolia's Minerals Law lets the state hold up to 34 per cent of the equity in the private company exploiting such a deposit, without compensation, when its proven reserves were determined without state budget funding.
Entrée met members of the working group, reconstituted on Oct. 2 and led by the Minister of Justice and Internal Affairs, on Nov. 9 and 10 to begin negotiations.
Under the framework, the parties will make reasonable efforts to resolve those issues within the first quarter, and may mutually agree to extend the talks if they cannot. They also acknowledge that Mongolia's Parliament has the authority to set the state's shareholding in the company holding the licences and to decide whether a special royalty replaces it.
Entrée's next step is to prepare a revised proposal for the working group in consultation with other stakeholders. Its non-binding proposal of March 25 contemplated a negotiated royalty in place of a 34 per cent state equity stake and drew no formal response, the Nov. 5 release said.
"The Company remains committed to working towards a constructive solution that serves the interests of all Oyu Tolgoi project stakeholders and enables OT LLC to resume Lift 1 underground development and extraction activities on the Shivee Tolgoi license area," Entrée said in the release.
Read more: Rio Tinto keeps 2026 guidance as Oyu Tolgoi copper output rises 27 per cent
Seven Infill Holes Returned Up to 1.45 Per Cent Copper Equivalent
Entrée also reported assays, received from Oyu Tolgoi LLC, for seven underground infill holes drilled at the Hugo North Extension deposit between 2023 and 2026. The best, UGD1025A, returned 125.31 metres grading 1.45 per cent copper equivalent from 362.69 metres down the hole.
That interval carried 1.28 per cent copper and 0.270 parts per million gold. UGD918A returned 67.6 metres grading 1.07 per cent copper equivalent, and UGD1016 returned no significant results.
The holes targeted the deposit's existing footprint in the proposed Lift 2 block cave or were drilled for geotechnical purposes, and results cover only the parts on the joint venture property. Lengths are drilled lengths, and Entrée estimates true widths at about 20 to 70 per cent of them for holes drilled across the porphyry trend.
Copper equivalent uses the metal prices in Entrée's technical report dated Oct. 8, 2021, including US$3.08 a pound for copper and US$1,292 an ounce for gold. Assays for five more underground holes and one surface hole are pending.
Entrée had US$2.5 million in cash at Sept. 30, before closing a C$36.2 million private placement on Nov. 4, according to its third-quarter release.
Entrée said on Nov. 5 it is targeting the first quarter of 2027 for an updated technical report on its joint venture interest.
Mara Quinlan