Marimaca Copper receives Chilean permit to begin early works at MOD copper project

The SERNAGEOMIN permit allows site preparation and bulk earth movement, while full-scale construction still awaits the board's final investment decision.

Mara Quinlan·
A mixed-media collage of a surveyor's level on a tripod and a row of survey stakes in a desert, overlaid with ink sketches of terraced ground and one copper brush stroke.
A collage of survey gear on desert ground with ink sketches of leach pad terraces. Illustration: Mugglehead, generated with AI.

Marimaca Copper Corp. TSEMARI ASXMC2 said on Thursday that its subsidiary has received a mining method sectorial permit from Chile's National Geology and Mining Service (SERNAGEOMIN) for the Marimaca Oxide Deposit (MOD). The permit allows site preparation and bulk earth movement to begin, while full-scale construction of a mine designed to produce 50,000 tonnes of copper cathode a year still needs a positive final investment decision from Marimaca's board.

Marimaca is a copper developer listed on the TSX and the ASX, and the MOD in Chile's Antofagasta region is its flagship project.

Shares rose 2.3 per cent to C$6.29 in Toronto by 11:05 a.m. EST on Thursday, according to the Google Finance quote page for TSEMARI. By then 34,930 shares had changed hands against a daily average of about 251,000, and the same page showed a market value of about C$853 million.

The permit was issued to Compañía Minera Cielo Azul Limitada, Marimaca's wholly owned subsidiary, according to the company's release. Detailed engineering, initial procurement and early works are under way in Chile as the project moves toward the investment decision, Marimaca managing director for Chile José Antonio Merino said in the release.

"The receipt of the Método de Explotación Sectorial Permit builds on the RCA (Environmental Approval) received in November 2025 and is another major milestone for the MOD, allowing for the commencement of the fully funded early works construction activities at the project," Merino said.

Read more: Marimaca Copper says panel upheld CEN approval of application to connect to 110 kV line

Marimaca's 2025 definitive feasibility study estimated pre-production capital costs of US$587 million for a heap leach operation with a 13-year mine life, according to the company's project page. It forecast average output of 48,000 tonnes of copper cathode a year over the first 10 years, including a one-year ramp-up.

At a three-month average COMEX copper price of US$5.05 a pound, the study gives an after-tax net present value of US$1.1 billion at an 8 per cent discount rate and an internal rate of return of 39 per cent. At US$4.30 a pound, the study gives a value of US$709 million and a return of 31 per cent.

Sprott's US$450 Million Term Sheet Is Non-Binding

Sprott Resource Lending Corp. has given investment committee approval to a proposed US$450 million financing package to support construction of the MOD, according to Marimaca's Tuesday release. The non-binding term sheet covers a senior secured project finance facility of up to US$425 million with a 7.5-year term and an equity investment of up to US$25 million.

Interest on the facility would accrue at 5.75 per cent a year plus the greater of SOFR and 2.75 per cent. A first US$100 million would be released upon the investment decision, subject to customary conditions including definitive documentation.

The package also remains subject to Sprott's legal and financial due diligence and to conditions precedent to financial close.

Marimaca said on Tuesday that it continues to advance the MOD toward a final investment decision, with critical path items on schedule through 2026 and 2027.