Silver X Mining Corp. CVEAGX OTCMKTSAGXPF reported on Thursday third-quarter net operating revenue of US$10.1 million, up 103 per cent from a year earlier, and a net loss of US$1.7 million. The company now expects its Recuperada plant in Peru to sustain 1,000 tonnes per day in the first quarter of 2027, having said on Oct. 8 it expected the plant to reach that rate in the fourth quarter.
Silver X is a silver producer whose Nueva Recuperada project covers 20,795 hectares and three mining units. Its silver-equivalent production in the third quarter was 225,237 ounces, up 35 per cent from a year earlier and down 20 per cent from the second quarter.
Shares of Silver X fell 13.2 per cent to C$0.46 by 1:23 p.m. EST on the TSX Venture Exchange on Thursday, according to the Google Finance quote page for CVEAGX. The shares had closed at C$0.53 on Wednesday, and about 1.29 million had traded by that time, more than twice the average daily volume of 590,230 shown on the page.
Mechanical issues with equipment installed for the expansion delayed the ramp-up beyond the schedule the company had disclosed, Silver X said in its third-quarter results release. The plant averaged 594 tonnes per day in the third quarter, down from 684 tonnes in the second quarter, while repairs and installation work constrained processing.
Throughput averaged 598 tonnes per day in October and 709 tonnes from Nov. 1 to 15, preliminary figures that the company said do not represent sustained operation at the target rate.
Metallurgical recoveries have been below the levels achieved earlier in 2026 during the ramp-up, particularly for lead, zinc and gold. Silver X is limiting throughput while it completes the remaining works and adjusts the flotation circuit, and it expects lower throughput and recoveries to affect fourth-quarter production and unit costs.
"The ramp-up has taken longer than planned, and we are addressing the equipment and processing issues directly," chief executive José M. Garcia said in the release.
Silver X said it no longer considers 2029 a reliable date for reaching 3,000 tonnes per day and annual production of more than six million silver-equivalent ounces. It cited the delay in achieving sustained throughput of 1,000 tonnes per day and the timing of environmental approvals.
An updated preliminary economic assessment, expected in the first half of 2027, will replace the production profile and schedule of the 2025 assessment. Expanding permitted capacity, including a new processing plant at Tangana, still depends on approval of an updated environmental and social impact assessment.
Revenue Fell 42 Per Cent From the Second Quarter
Net operating revenue for the three months to Sept. 30 fell from US$17.3 million in the second quarter, mainly reflecting a 27 per cent drop in silver-equivalent ounces sold. The decline also reflected lower realized precious metal prices and negative provisional pricing adjustments.
The average realized silver price was US$63.00 an ounce in the quarter to Sept. 30, against US$72.67 in the second quarter. All-in sustaining costs rose to US$49.01 per silver-equivalent ounce from US$46.10.
Read more: COMEX gold and silver futures gain ahead of the Wall Street open
Silver X held US$43.3 million in cash and US$26.7 million in working capital at Sept. 30. The gain in liquidity since Dec. 31, 2025 mainly reflects a secured convertible debenture financing in March that brought in net proceeds of US$46.6 million and carries 10 per cent annual interest.
Silver X has scheduled the remaining installation work for completion in early December, with recoveries to be restored before processing rates increase.
Mara Quinlan