Applied Optoelectronics signs hyperscaler deal with US$2.2B in minimum purchases

U.S.-made shipments are due to start in early 2027, and the unnamed buyer made no capital commitment under the four-year agreement.

Julian Okafor·
Gold wires are visible on a small metal component against a blurred background.
A close-up of a metal component with gold wires. Illustration: Mugglehead, generated with AI.

An existing hyperscale customer has agreed to about US$2.2 billion in minimum purchases of optical networking components, with most of the commitment concentrated in 2027. Applied Optoelectronics, Inc. NASDAQAAOI, a Sugar Land, Texas, maker of optical and cable networking equipment, said Nov. 24 it signed a four-year supply agreement covering 800G transceivers and laser diodes.

The buyer committed to about US$1.5 billion in transceiver purchases in 2027. The minimum for laser diodes is about US$700 million for 2028 and 2029 combined. The two commitments cover three calendar years of an agreement that runs from December 2026 through December 2030. Applied Optoelectronics did not name the buyer in the announcement.

Applied Optoelectronics shares rose 17.5 per cent to US$38.70 at Monday's 4:00 p.m. EST Nasdaq close, according to NASDAQAAOI. The Nov. 23 close preceded the announcement.

Applied Optoelectronics agreed to a one-time US$2 million expense to speed qualification work under the Nov. 24 deal, while the buyer made no capital commitment. The two sides can add products as the customer's needs change. The announcement gives purchase commitments in dollars by product category without disclosing unit prices or a breakdown of shipment volumes.

The Demand Forecast Exceeds the Purchase Minimum

“While not guaranteed, the current level of demand based on long-term discussions with the customer exceeds $10 billion over the four years of the LTA,” Applied Optoelectronics chief financial officer and chief strategy officer Stefan Murry said in the Nov. 24 announcement.

The US$10 billion figure discussed on Nov. 24 is an indication of demand, not a purchase order or company revenue guidance. To turn demand above the minimum into sales, Murry says Applied Optoelectronics needs to expand capacity and secure further purchase commitments. The company also cited product qualification, delivery timing and contractual conditions affecting purchase volumes as risks to what it ultimately sells under the agreement.

Founder and chief executive Thompson Lin described the new deal as a long-term agreement with a second hyperscaler. The company had already reported a multiyear agreement with a hyperscale customer in its Nov. 5 results. Those results put third-quarter revenue at US$269.9 million, up from US$118.6 million in the same period of 2025. The company posted a US$6.3 million net profit for the quarter after a US$17.9 million loss a year earlier.

Applied Optoelectronics forecast fourth-quarter revenue of US$385 million to US$420 million on Nov. 5. That outlook covers the whole business, while the US$1.5 billion purchase minimum is for one customer's transceivers in 2027.

Coherent Corp. NYSECOHR, a photonics manufacturer, reported US$2.37 billion in revenue for its fiscal first quarter ended Sept. 30. Revenue rose 50 per cent from a year earlier, Coherent said on Nov. 4. At Monday's 4:00 p.m. EST New York close, the shares were up 15.4 per cent at US$215.81, according to NYSECOHR.

A similar distinction between signed commitments and potential revenue came up in Mugglehead's Nov. 23 coverage of an 18-year hyperscale data centre lease. The lease figures separated revenue over the initial term from additional rent that depended on the tenant exercising renewal options.

Read more: Applied Digital Corporation signs US$5.4B AI data centre lease

U.S.-Made Shipments Are Scheduled for Early 2027

Applied Optoelectronics said on Nov. 5 its manufacturing equipment capacity was approaching 330,000 units per month. It expects to have equipment in place by the end of 2026 with capacity for more than 500,000 pieces of 800G and 1.6 Tb products per month. The combined target does not give a separate figure for 800G, the transceiver speed covered by the new agreement.

The company is targeting monthly capacity of more than one million transceivers across those two speeds by the end of 2027. It said on Nov. 5 that its 2027 U.S. capacity expansion plan would take longer than expected because of delays getting electrical power and other construction issues.

Applied Optoelectronics expects to start supplying laser diodes in 2028, with some likely to be used in co-packaged optics, Lin said in the Nov. 24 announcement. He said the company plans to expand its Texas laser manufacturing capacity to meet expected demand for high-power lasers.

The equipment installation target falls at the end of December 2026. The first delivery milestone for U.S.-made products comes in the first quarter of 2027, when Applied Optoelectronics says it must start shipping an agreed quantity under the new deal. Those shipments are to increase through 2027.