By Nov. 24, limited work had resumed at the planned 6.9-megawatt Highway 28 solar installation in New York, PowerBank Corporation (Cboe Canada) NASDAQPBK FRA103 said. The award can reimburse up to US$952,583 in eligible costs of implementing the site's required stormwater pollution prevention plan. PowerBank said the award came through the Catskill Watershed Corporation, a watershed protection nonprofit, but gave no reimbursement schedule.
PowerBank estimated the site's development and construction value at US$17 million on Nov. 24. Existing approvals cover site preparation and limited civil work to manage runoff, while full construction still needs financing and the remaining permits.
PowerBank develops and owns distributed solar and battery storage assets in Canada and the United States. Its shares closed at C$0.125 on Nov. 23, according to Cboe Canada's Nov. 24 quote page.
PowerBank said on Nov. 24 that the stormwater award and US$893,445 in previously approved state support would amount to about US$1.85 million if the full grant were reimbursed. The approved state money comes from the New York State Energy Research and Development Authority's NY-Sun program, according to PowerBank's Aug. 18 acquisition announcement.
PowerBank said in its Nov. 24 update that it expects Highway 28 to qualify for about US$1.52 million through the authority's Inclusive Community Solar Adder program. The company did not report approval of that additional incentive or give a disbursement date for the existing NY-Sun award.
PowerBank said on Aug. 18 that it reacquired Highway 28 through its U.S. subsidiary Abundant Solar Power Inc. for US$1,249,488, payable in milestone instalments. Abundant had started preparing the site as the engineering, procurement and construction contractor before full mobilization.
Full Construction Still Needs Financing and Permits
The August announcement said Highway 28 had secured an interconnection agreement and all major discretionary permits. PowerBank did not identify the permits still needed or the agencies responsible for issuing them in its Nov. 24 release.
"Full construction remains subject to project financing and receipt of the remaining permits," PowerBank said in its Nov. 24 release.
PowerBank estimated a potential federal investment tax credit of about US$8 million on Nov. 24. The company says physical work began before July 5, 2026, and expects that work to satisfy the Internal Revenue Service's Physical Work Test. It says eligibility still depends on meeting federal requirements, including continuity of construction.
PowerBank outlined a sale option in November that would transfer ownership to a buyer while leaving the company with the construction work. It could instead arrange financing and add Highway 28 to its portfolio of operating assets, or use elements of both approaches. The update did not name a prospective buyer or disclose a price or term for power sales.
PowerBank estimated on Nov. 24 that Highway 28 could supply the equivalent of roughly 862 homes' annual electricity use once operating.
Read more: Collective Mining backs community solar project for 2,000 residents in Colombia
The Nov. 24 release gave no dates for securing financing or the outstanding permits and did not set an in-service date.
Ines Halvorsen