OMERS and Blackstone-backed TDI form Toronto Third Line bidding team

Ontario targets a mid-2027 procurement launch, while the partners disclose no investment amount or construction commitment.

Ines Halvorsen·
A thick submarine power cable passes through a stern roller on a generic work barge beside a concrete quay.
A generic submarine power cable on a work barge illustrates an underwater transmission proposal. Illustration: Mugglehead, generated with AI.

Ahead of a planned mid-2027 competition for a roughly 65-kilometre electricity line, OMERS and Blackstone Inc. NYSEBX subsidiary Transmission Developers Infrastructure - Canada Co. formed a bidding partnership on Wednesday. Their Nov. 18 announcement disclosed no investment amount or expected revenue for the proposed Toronto Third Line.

The Independent Electricity System Operator would select the transmitter and sign a procurement contract lasting no more than two years beyond commercial operation, subject to contractual adjustments. That is the framework in Ontario's June 18 directive.

Blackstone, an alternative asset manager, has indirect exposure through its ownership of TDI. The release announces a team seeking work and sets out no partnership ownership split, financing package or construction commitment. OMERS is a jointly sponsored defined benefit pension plan whose members include municipal, transit, utility and emergency-service employees in Ontario.

Read more: Blackstone Digital Infrastructure Trust agrees to US$5B data-centre deal

Blackstone's NYSEBX quote showed US$120.19 at the Nov. 13 close in New York, as of 4:02 p.m. EST, before the partnership announcement.

The planned connection would run beneath Lake Ontario between Bowmanville Switching Station in Clarington and Toronto's Port Lands. OMERS brings infrastructure investment experience, while TDI contributes the management, development and construction team behind the Champlain Hudson Power Express.

A June 16 completion notice described CHPE as a 1,250-megawatt connection from Quebec to New York City. Wednesday's partnership release says commercial operation began in May 2026.

The partners' Nov. 18 release describes approximately 236 kilometres of underground cable and 309 kilometres underwater on the New York line. It also points to a converter station built in densely populated Queens as relevant experience for Toronto's Port Lands.

"Working collaboratively with Indigenous communities, municipalities, regulators, suppliers and other stakeholders would be central to our approach throughout development and construction," TDI chairman Brian Kubeck said in the release.

The Winning Transmitter Must Secure Permits

The IESO's Oct. 1 planning presentation puts the route at approximately 65 kilometres. The selected transmitter would be responsible for route development, permits, regulatory approvals and Indigenous consultation.

Ontario's June 18 directive requires bidders to demonstrate experience developing, financing and constructing underwater and HVDC transmission infrastructure. They must also demonstrate an ability to work with manufacturers experienced in designing converter facilities and cables.

Those are qualification requirements; the partnership announcement identifies no cable or converter supplier or equipment delivery schedule.

Bidders must submit an Indigenous Engagement and Participation Plan with proposed minimum economic commitments, including any equity participation and opportunities in supply chains, training and employment. For those plans, the directive prohibits proponents from binding Indigenous communities through exclusive arrangements.

The procurement contract would limit and determine the capital costs entering the line's asset value or rate base, which would be regulated by the Ontario Energy Board from commercial operation. Wednesday's partnership announcement does not establish a construction budget or a regulated return for Blackstone.

The next procurement milestone is a launch targeted for mid-2027. Ontario has directed the IESO to endeavour to launch by then and conclude the competition by early 2028.