Graphene Manufacturing Group reports quality gains at higher production rate
The board approved A$1.26 million in added spending, mainly for the plant’s power systems and setup work at the separate Fulcrum facility.

On Nov. 25, as it worked toward a capacity of 10 tonnes a year, Graphene Manufacturing Group Ltd. CVEGMG OTCMKTSGMGMF said its Gen 2.0 graphene plant moved closer to its quality targets while running at a higher rate. The board approved another A$1.26 million, mainly for final generators and batteries at the plant and for setting up the separate Fulcrum facility, GMG said in its Nov. 25 release. The release did not name an equipment supplier or give a delivery schedule.
GMG did not say how much faster the plant ran, how long it held the higher rate or which quality measures improved. The company expects the plant to be capable of producing 10 tonnes of graphene a year once it is fully completed and optimised. The update did not report a sustained run at that rate.
GMG shares CVEGMG finished 7 per cent lower at C$1.32 on the TSX Venture Exchange at 4 p.m. EST on Nov. 24, before the plant update.
The Australian company makes graphene from natural gas for products including a heat-transfer coating and a lubricant additive. It reported A$724,152 in revenue from coating sales and installation and online lubricant sales in its annual report for the year ended June 30, 2026.
“Our focus now is on keeping that quality steady as we keep increasing output towards the plant's expected 10 tonnes per annum,” GMG chief executive Craig Nicol said in the release.
Nicol said GMG was on track to supply more graphene for its coatings, lubricants and battery products. The company is developing graphene batteries and has made a graphene slurry intended as an additive for lithium-ion cells.
Read more: Amprius Technologies wins up to US$75M grant for domestic battery line
On-Site Power Work Is Still Underway
GMG said on July 6 that it had started the plant before the end of June. At the time, it expected the capital cost to come in at or below A$2.3 million by the end of 2026. The Nov. 25 release did not give an updated total for the plant or say how the additional spending would be divided between the two sites.
GMG expects the plant to generate most of its own power once the work is complete. Its plan combines renewable generation and battery storage with generation fuelled by hydrogen-enriched natural gas. Nicol said the company was installing the final generators and battery systems.
GMG plans to assemble modular graphene production units at Fulcrum, a leased warehouse in Brisbane’s Richlands suburb near its existing plant. The board had approved A$1.2 million for design, engineering and procurement of equipment with long delivery times, GMG said on July 8. The company said then that it expected Fulcrum to take several years to complete, with funding to be approved in stages.
The Nov. 25 update did not say when the plant could attain its stated capacity. GMG’s July 6 schedule had targeted the end of September for work on quality, production rate and packing. Its July 8 release targeted the end of 2026 for completing that work and the plant’s on-site power systems.
Ines Halvorsen