Duke Energy wins North Carolina rate hikes and new data centre rules

New rates begin Jan. 1, 2027, while the orders approve shareholder-funded aid and financial safeguards for large data centre connections.

Ines Halvorsen·
An editorial collage shows an electricity meter and its service conduit against a weathered brick utility wall.
An electricity meter and service conduit illustrate utility rates. Illustration: Mugglehead, generated with AI.

A 3.7 per cent average annual rate increase takes effect Jan. 1, 2027, at the Carolinas utility of Duke Energy Corporation NYSEDUK following North Carolina's approval Monday. The package also approves US$20 million in shareholder funding to help customers in need, Duke said in its announcement.

The North Carolina Utilities Commission approved two-year plans for Duke Energy Carolinas and Duke Energy Progress. The Progress utility received average annual increases of about 3.4 per cent, alongside requirements intended to protect existing customers from the financial risks of new data centres.

Duke shares traded lower at US$130.17 on the NYSE at 2:05 p.m. EST on Nov. 17, according to NYSEDUK.

Residential increases run above the averages across all customer classes. Duke's summary puts the average annual residential increase at 4.8 per cent for Carolinas and 4.7 per cent for Progress over the two-year period.

For a Carolinas household using 1,000 kilowatt-hours a month, the projected bill increase is US$6.53 on Jan. 1, 2027. A further US$4.66 is projected for Jan. 1, 2028.

For a Progress household with the same consumption, the projected increase is US$9.62 on Jan. 1, 2027. A further US$5.89 is projected for Jan. 1, 2028. Duke said agreements with customers and other stakeholders reduced its original requests for both utilities.

"This outcome keeps affordability at the forefront while allowing us to make the investments needed to strengthen reliability and support North Carolina's continued growth," Duke Energy North Carolina president Kendal Bowman said in the release.

Data Centres Face Upfront Payments And Security

The orders establish a new rate schedule for data centre customers with loads above 50 megawatts, according to Duke. They approve many existing requirements and add terms covering upfront payments for dedicated facilities, financial requirements for transmission upgrades and security against potentially stranded generation investments.

The commission issued separate orders in the Carolinas rate case and the Progress rate case. Only the opening portions of those lengthy orders were available for review; the detailed rate and customer-protection provisions reported here come from Duke's summary.

The distinctions separate the costs of connecting an individual customer from the risk of building generation to serve future demand. Duke describes the security requirements as addressing potential stranded generation investments, while dedicated facilities require payments upfront.

Read more: Fermi signs US$200M prepayment agreement for 600 MW Texas development

The orders also require refunds, with interest, if Duke does not complete planned infrastructure upgrades on time. Together with the shareholder contribution, that provision places financial obligations on the utility alongside the higher customer charges.

Carolinas serves central and western North Carolina, while Progress serves central and eastern areas and the Asheville region. The utilities combine on Jan. 1, 2027, but their rates will remain separate, Duke said.

The next billing milestone is Jan. 1, 2027, when the approved increases take effect. Rate blending will occur gradually through later rate cases and rider filings at a pace set by the commission.